Stream II

Battery Energy Storage System

Green power storage

Battery Energy Storage Systems (BESS) have rapidly developed into a key component of the energy transition in Germany.

BESS act like a large rechargeable battery for the grid capturing excess energy from renewable energy sources or low-priced grid power and releasing it during peak demand, outages, or when renewables aren't producing, thus stabilizing the grid, increasing renewable integration, and providing backup power.

The “Ruperti II” drilling permit has sufficient area to install a 10MWe BESS and will be integrated with the geothermal heat, cooling and power generation facility.

The aim is for the BESS to be charged by the geothermal power plant, Additionally, the BESS can help optimise production from the geothermal plant and support the Kirchanschöring electricity network.

Image: Illustration of a 10MWe BESS on a site adjacent to an access road and a railway line. Source: ChatGPT.

BESS timeline

The BESS will be designed and integrated into the geothermal heat, cooling and power generation facility.

February 2026

Ownership of GTR passed to ZeroGeo Energy GmbH

1st Quarter 2026

Techno-economic studies to determine potential of Green Energy Hub business streams

2nd Quarter 2026

Agreements with BESS partner

3rd Quarter 2026

Detailed technical and engineering studies to define work programme to install BESS

October 2026

Final Investment Decision Stream II

4th Quarter 2026

Tendering for BESS equipment and site preparation. Purchase of long lead items

1st Quarter 2027

BESS installation

2nd Quarter 2027

BESS installation